B-Block Demolition Completed – April 2017

B-Block main building, B-Fan and B-Tail have now been demolished to make way for the construction of K-Block. Load out of demolition materials is underway.

Click on each image for a larger view.

back to top


Demolition of B-Block - March 2017

Passers-by can see progress at the Royal Hobart Hospital Redevelopment site with demolition works breaking through the main building on Campbell Street late last week.

These photographs of B-Block were taken on Monday 6 March 2017.

Click on each image for a larger view.

back to top


Temporary Inpatient Facility – J-Block Completed – January 2017

The 64 pre-fabricated modules were installed and the facility, known as J-Block, was commissioned and received patients in November 2016.

Click on each image for a larger view.


Aerial view of J Block and RHH

back to top


Temporary Inpatient Facility - Steel Supporting Structure - February 2016

Images of the steel gantry installed in the Liverpool Street forecourt of the Royal Hobart Hospital campus. The steel gantry will support the pre-fabricated modules of the temporary facility.

Click on each image for larger view.


back to top


Baseline - 2015

Images of the Royal Hobart Hospital above Liverpool Street – includes the Liverpool Street forecourt, C-Block, H-Block (on the right) and A-Block (on the left).

Click on each image for larger view.

Royal Hobart Hospital above Liverpool Street – includes the Liverpool Street forecourt, C-Block, H-Block (on the right) and A-Block (on the left)Royal Hobart Hospital above Liverpool Street – includes the Liverpool Street forecourt, C-Block, H-Block (on the right) and A-Block (on the left)Royal Hobart Hospital above Liverpool Street – includes the Liverpool Street forecourt, C-Block, H-Block (on the right) and A-Block (on the left)Royal Hobart Hospital above Liverpool Street – includes the Liverpool Street forecourt, C-Block, H-Block (on the right) and A-Block (on the left)Royal Hobart Hospital above Liverpool Street – includes the Liverpool Street forecourt, C-Block, H-Block (on the right) and A-Block (on the left)Royal Hobart Hospital above Liverpool Street – includes the Liverpool Street forecourt, C-Block, H-Block (on the right) and A-Block (on the left)

back to top


Time-lapse Videos

Demolition and Load Out

Watch the demolition of B-Block and the removal of building materials from site March to May 2017.

Watch the first two weeks of the demolition of the main B-Block building.

Installation of the Temporary Inpatient Facility

Watch a week in the life of the construction of the temporary Liverpool Street forecourt facility.

back to top